1. Sidewalks are required for all new development and redevelopment. This
requirement may be mitigated via payment into the Pedestrian
Circulation Fund at the City's discretion.
NOTED
2. Show stormwater flow and outfall to public conveyance on plans.
WILL REVISE
3. Revise language in planting schedule regarding shrub size - must meet
Section 21-54.02(e) (minimum height of 24 ").
WILL REVISE
4. Add general note stating, "All disturbed areas are to be sodded ".
WILL REVISE
5. Show irrigation plan.
WILL REVISE
6. Show distance from proposed driveway to adjacent driveway. (Per Order
of Non-Administrative Variance the distance must be 6')
WILL REVISE
Building Dept
The following comments are directed:
1. Construction plans must be sealed by an engineer to the FBC 2004 with
the 2006 revisions and NEC 2005.
NOTED
2. The property must meet the minimum requirements for accessibility.
Chapter 11 of the Florida Building Code will apply to this situation.
NOTED
3. Plans must be submitted detailing the accessibility and the means of
compliance before construction can begin.
NOTED
Environmental Services
1. There are no Erosion Control Notes on the plans as stated in
Construction Note #2. Please note that one of the requirements in the
erosion control notes shall be a statement that a dumpster or other
container sufficient in size to contain all waste generated during
construction shall be provided.
WILL REVISE
2. The water and sewer connections should be shown on the plans.
WILL REVISE
Legal Dept
Based on review of the documents submitted, it appears that the items
submitted are compliant with no outstanding issues.
Therefore, the Legal Department would approve pursuant to the following*
1. Compliance with the Order of Non Variance of record;
NOTED
2. If there is a mortgage holder, mortgage holder will need to execute
joinder or letter of authorization if property is encumbered; and
NOTED
3. Compliance with all City, County, State and Federal requirements,
including the City of Edgewater's Code of Ordinances and Land
Development Code.
NOTED
Engineer
1. The plans should include a note stating, "All construction shall in
conformance with the City of Edgewater Land Development Code and
Standard Construction Details, Latest Version, unless otherwise
specifically approved.
NOTED
2. All disturbed pervious areas should be sodded and pertinent notes added
to site plan.
NOTED
3. Applicant to prove capacity of proposed retention system to recover its
required treatment volume within 72 hours.
NOTED
4. An FDOT permit /modification is required for driveway to US —1
improvements and stormwater connection.
NOTED
Fire Dept
1. The required fire flow for this project is 1500 GPM.
NOTED
These comments are intended to comply with City of Edgewater Land Development
regulations, FDOT standard specifications and sound engineering practices, and are
not meant to be inclusive of all errors or omissions. The engineer of record is solely
responsible for technical accuracy, engineering judgment, and quality of work.
While every effort is made to assure that projects reviewed by this office comply with
all applicable codes and standards, we do not certify or guarantee that they do. It is
the responsibility of the applicant to assure compliance with all applicable codes and
standards prior to the project being issued a certificate of occupancy.