10-26-2015 - Whistle Stop Park Workshop frF s 104 N.Riverside Drive
City of Edgewater
Edgewater,FL 32132
f
EDGEzWATER Meeting Minutes
City Council
Michael Ignasiak,Mayor
Christine Power,District 1
Gigi Bennington,District 2
Dan Blazi,District 3
Gary T. Conroy,District 4
Monday,October 26,2015 6:00 PM Council Chambers
Whistle Stop Park Workshop
1. CALL TO ORDER,ROLL CALL,PLEDGE OF ALLEGIANCE,INVOCATION
Mayor Ignasiak called the meeting to order at 6:00 p.m.
Present: 5- City Clerk Bonnie Brown,City Manager Tracey Barlow,Councilman Dan Blazi,Mayor
Mike Ignasiak,and Councilwoman Christine Power
Excused: 3- City Attorney Aaron Wolfe,Councilman Gary Conroy,and Councilwoman Gigi
Bennington
2. PRESENTATIONS
City Manager Barlow made a staff report, and discussed.- the purpose of the Whistle Stop Workshop
being to discuss conceptual plans of the major renovations, before going to the ballot for residents to
vote; the process, or steps, the meeting will follow; amenities to be considered as part of the
renovation, however, looking at the flow, and theme of the renovations, but not getting into the
weeds; and recommended Council to charge the Recreational and Cultural Services board with
working on the renovation details, and developing a draft plan to bring back to Council. He also
stated that other topics covered during the workshop would be: amenities that will stay in place;
timelines, and steps taken during each phase; the bond, and projected maximum renovation costs;
and what the costs would look like on a tax bill for the average household.
a. AR-2015-125 Whistle Stop Park Redevelopment
2
Shailesh K Patel, Dredging & Marine Consultants, LLC, made a presentation, and stated they would
discuss renovation concepts and options; and the City's resident survey, and resident's top five (5)
renovation choices.
Mr. Patel stated that the resident's top five choices were: an all-inclusive playground, with shade;
improved restrooms; a family style splash park; new pavilions capable of hosting things like birthday
parties; and walking trails. He discussed: amenity options, and possible placement of each of the
amenities; parents wanting to maintain visibility of their children at all times; roads, parking
requirements, stormwater requirements, and use of green space for parking; adding a dog park to the
design plans; estimated costs of each option; park lighting options; additional parking (using more
pavement), and the effect on costs; and design options, and possibly doing the renovations in phases.
City of Edgewater Page I Printed on 111312015
City Council Meeting Minutes October 26, 2015
Council, staff, and Mr. Patel discussed. hybrid options of all the models; options to adding the dog
park; traffic calming devices; traffic difficulties during school hours, and traffic
planning/management; pavilion options at the retention pond area, and possible uses; location for
the proposed splash park and dog park; senior citizen/adult exercise and fitness area options;
options for keeping the open space for family use; shade trees and their affect on park use; racquet
ball, tennis courts, and security lighting; turf options for the dog park; options and costs
comparisons; switching the locations for the dog park and skate park; keeping the skate park
location near the center of the park; a larger pavilion; a senior fitness area north of the tennis
courts; using option number four, with a dog park added to it; sidewalk route options; and parking
options, and the walking trail.
Leisure Services Director, Jack Corder made a staff presentation.
During his presentation, Council and staff discussed: various playground designs, equipment
options, and costs; themes, such as keeping the playground as a natural design; using calming color
schemes, and parents being able to easily spot their children; using the expertise of the Recreation
and Cultural Services Board to make aesthetic design decisions, and Council sticking to the overall
theme; the park theme being the guiding principle for what the park will look like; reasons not to
rename Whistle Stop park; possibly designing the park theme around the Whistle Stop park name;
and taking into consideration Florida's weather conditions, and using practical colors.
After discussion, the Council concurred not to rename Whistle Stop park.
Council and staff discussed: the parks entire theme being designed around the "Whistle Stop" name;
types of playground surfaces, National standards, maintenance, and costs; splash park surface
options, water bourne diseases, safety/risks, and using concrete with an acrylic surface; not charging
for using the splash park; splash pad options; fencing options; developing a fenced hybrid children
play ground area/splash pad,- concurring to use a solid surface for the splash pad,- and the positive
aspects of having two (2) separate, but adjacent splash pads, with one being fenced in, and just for
younger children.
Councilwoman Power departed at 7:06 p.m.
Walt Zakaluzny, 3022 Silver Palm Drive voiced concerns about the planned skate park being right
next to the children area, older kids setting a bad example for children, and safety issues. The
Council, and staff discussed the positive influences on kids behavior when a skate park is located
close to areas with families and adults.
City Manager Barlow distributed, reviewed, and discussed, a projected Whistle Stop Park renovation
project timeline.
Councilwoman Power rejoined the workshop at 7:14 p.m.
Finance Director John McKinney discussed: the issuance of a three (3) million dollar general
obligation (GO) bond, with an issuance date of June or July 2017; front ending costs, which would
be reimbursed by the GO bond; based on what he believes to be the highest interest rate, a three (3)
City of Edgewater Page 2 Printed on 111312015
City Council Meeting Minutes October 26, 2015
million dollar loan would be roughly a $200,000 annual debt service; that would translate to a .302
millage rate for home owners; using a homeowner with a home valued at $150,000, with a $50,000
exemption, that would bring the homeowners annual GO bond costs to somewhere around $28 to $29
a year; if the City were to go to the extreme high end of a $3.5 million dollar GO bond, the annual
costs per household would be $32.21, for 25 years; and the City Manager's recommendation not to
finance any park renovations for longer than 20 years.
Mr. McKinney stated that based on the City Manager's recommendation not to finance any park
renovations for longer than 20 years, he will have everything put together to discuss a $3 million
dollar loan; and Mr. Barlow stated the numbers would be ready for Council's November meeting.
The Council and staff discussed.- inflation costs; doing a numbers break out up to $3.5 million
dollars; the loan issuance resolution; submitting for grant funds; and that unused loan revenue can
be used to renovate other City parks.
Councilman Blazi stated that he usually does not attend City board meetings; and asked everyone not
to misconstrue his attendance at the Recreation and Cultural Services Board meetings as providing
guidance; that he is just very excited about the park renovations the project.
Mr. Corder stated that this is a very interesting project; and asked everyone to keep an open mind,
because there are so many variables when it comes to designing parks; and if anyone wants to share
their ideas, to send them to him so he can provide them to the board.
Mr. Barlow discussed.- staff having their work cut out for them; hopefully, by the first part of the
year, having a good realistic concept plan to showcase that people can relate to; providing residents
with information so they can make a good informed decision; and getting direction from who we all
work for, the residents of Edgewater.
3. ADJOURN
Mayor Ignasiak thanked everyone for their well received presentations, and adjourned the meeting at
7:26 p.m.
Minutes submitted by:
Mitch Honaker
Deputy City Clerk
City of Edgewater Page 3 Printed on 111312015
•
•
z
n ..
r � �
,t s
a Ctflt C
Y � `ttttttttt�
C NNNNNNpIt
C r r ttrtrttrNt�te
V INtttH yttttt,
Ct�Ct�O ICIlI i
C
t ttC
tt CIlI NNCI ItN
�' tOt CIOICIOICG ..
•�•.... �� �I mow,
01,
s ,
/1
1
o �o
..
LL
M O
w0
u0
@ 0
0
N
Q
W
1 oo `t (n 0
♦ � � wa
4t
0
w
U�
.,•, z
ol
t ,% .ai :+. O
0
W J J
.01
0 0
H H
, &� '� � �? • bmAiM�eYsa
CITY OF EDGEWATER - WHISTLE STOP PARK
Conceptual Plan Cost Estimate - Option 1
ITEM # DESCRIPTION QTY UNIT PRICE/UNIT PRICE
1 Mobilization/Demobilization 1 LS $ 60,000.00 $ 60,000.00
2 Construction Survey&As-Built Survey 1 LS $ 15,000.00 $ 15,000.00
3 Environmental Compliance 1 LS $ 15,000.00 $ 15,000.00
Earthwork
4 Clearing, Grubbing and Hauling 1 LS $ 20,000.00 $ 20,000.00
5 Demolition and Hauling 1 LS $ 35,000.00 $ 35,000.00
6 Grading and Compaction 1 LS $ 30,000.00 $ 30,000.00
7 Fill 1,000 CY $ 12.00 $ 12,000.00
Hardscape
8 10'Concrete Trail 3,320 LF $ 45.00 $ 149,400.00
9 5'Sidewalk 1,065 LF $ 20.00 $ 21,300.00
10 Type"D"Curb 4,800 LF $ 20.00 $ 96,000.00
11 Asphalt Parking & Roadway 88,400 SF $ 3.00 $ 265,200.00
12 Signage 1 LS $ 10,000.00 $ 10,000.00
13 IStriping 1 1 LS $ 10,000.00 $ 10,000.00
14 lEntrance Signs 1 2 1 EA $ 5,000.00 $ 10,000.00
Buildings
15 N. Restroom Building (inc.electrical and plumbing) 1 LS $ 270,000.00 $ 270,000.00
16 S. Restroom Building (inc.electrical and plumbing) 1 LS $ 97,200.00 $ 97,200.00
17 Building Electrical Connection 2 LS $ 5,000.00 $ 10,000.00
18 Building Water Connection 2 LS $ 15,000.00 $ 30,000.00
19 Building Sewer Connection 2 LS $ 15,000.00 $ 30,000.00
Amenities
20 ISplashpark 1,960 SF $ 130.00 $ 254,800.00
21 Playground-Equipment&Soft Surfacing 1 LS $ 150,000.00 $ 150,000.00
22 Skate Park 12,700 SF $ 20.00 $ 254,000.00
23 Basketball Court 1 LS $ 36,000.00 $ 36,000.00
24 Dog Park 1 LS $ 25,000.00 $ 25,000.00
25 Large Pavilion 2 1 EA $ 50,000.00 $ 100,000.00
26 Small Pavilions 8 EA $ 10,000.00 $ 80,000.00
27 Grills 10 EA $ 300.00 $ 3,000.00
28 Picnic Tables 20 EA $ 2,200.00 $ 44,000.00
29 Benches (6') 9 EA $ 1,200.00 $ 10,800.00
30 Splash Park and Playground Concrete 11,300 SF $ 5.00 $ 56,500.00
Stormwater and Utilities
31 Stormwater Construction 1 LS $ 55,000.00 $ 55,000.00
32 Parking Lighting 1 LS $ 80,000.00 $ 80,000.00
33 Electrical Distribution 1 LS $ 100,000.00 $ 100,000.00
Landscaping&Amenities
34 Landscaping 1 LS $ 25,000.00 $ 25,000.00
35 Irrigation 1 LS $ 5,000.00 $ 5,000.00
36 Trash Receptacles 20 EA $ 450.00 $ 9,000.00
Design
37 lEngineering and Permitting 1 LS $ 200,000.00 $ 200,000.00
SUBTOTAL $ 2,674,200.00
Contingency(5%) $ 133,710.00
TOTAL $ 2,807,910.00
Pagel
2131t1M3J43 JO)1110 N3 sa ca o va ns ---.p--, S1SIlN310S•S2133N19N3
9o99-b0£(99£)
so99-rooul9aE)uogd xaj z£1ae BffLVtiia0el3
lj'a31VM3�Jo3
vo-sso-slatla S1N3W3A021dW1 szlzE a as6e,pr,od
'aa 3a1sa3nia
JI21tJd dOlS 3l1SIHM Z0E'No moa HiaoNro°1
Z lt/f11d30N00 N p,re su,ow ap,ta's£b9ro si enNs oo a�,ew g s�sPa,❑
3WVN iOAPO ld
Sk
d
v
Gf•.,
i
t
p
",o
O
O
. w
µ
y
1/�\\ �'..... ply � •
O �
Y
pk.l
1
l
SLO6/£?/6LN e14e1 JWa Ag 6m y uoW\s6uImI—dde15 aI1 IM OUSYUS LUdercWPPoa--J31'W,d D—ZaweNfiuimerp
CITY OF EDGEWATER - WHISTLE STOP PARK
Conceptual Plan Cost Estimate - Option 2
ITEM # DESCRIPTION QTY UNIT PRICE/UNIT PRICE
1 Mobilization/Demobilization 1 LS $ 60,000.00 $ 60,000.00
2 Construction Survey&As-Built Survey 1 LS $ 15,000.00 $ 15,000.00
3 Environmental Compliance 1 LS $ 15,000.00 $ 15,000.00
Earthwork
4 Clearing, Grubbing and Hauling 1 LS $ 20,000.00 $ 20,000.00
5 Demolition and Hauling 1 LS $ 35,000.00 $ 35,000.00
6 Grading and Compaction 1 LS $ 30,000.00 $ 30,000.00
7 Fill 1,000 CY $ 12.00 $ 12,000.00
Hardscape
8 10'Concrete Trail 3,320 LF $ 45.00 $ 149,400.00
9 5'Sidewalk 1,473 LF $ 20.00 $ 29,460.00
10 Type"D"Curb 5,000 LF $ 20.00 $ 100,000.00
11 Asphalt Parking & Roadway 87,600 SF $ 3.00 $ 262,800.00
12 Signage 1 LS $ 10,000.00 $ 10,000.00
13 IStriping 1 1 LS $ 10,000.00 $ 10,000.00
14 lEntrance Signs 1 2 1 EA $ 5,000.00 $ 10,000.00
Buildings
15 N. Restroom Building (inc.electrical and plumbing) 1 LS $ 270,000.00 $ 270,000.00
16 S. Restroom Building (inc.electrical and plumbing) 1 LS $ 97,200.00 $ 97,200.00
17 Renovation Existing Restroom/Storage Building 1 LS $ 115,000.00 $ 115,000.00
18 Building Electrical Connection 2 LS $ 5,000.00 $ 10,000.00
19 Building Water Connection 2 LS $ 15,000.00 $ 30,000.00
20 lBuilding Sewer Connection 2 LS $ 15,000.00 $ 30,000.00
Amenities
21 Splashpark 1,500 SF $ 130.00 $ 195,000.00
22 Playground-Equipment&Soft Surfacing 1 LS $ 150,000.00 $ 150,000.00
23 Skate Park 11,000 SF $ 20.00 $ 220,000.00
24 Basketball Court 1 LS $ 36,000.00 $ 36,000.00
25 Dog Park 1 LS $ 25,000.00 $ 25,000.00
26 Medium Pavilion 4 EA $ 25,000.00 $ 100,000.00
27 Small Pavilions 4 EA $ 10,000.00 $ 40,000.00
28 Grills 9 EA $ 300.00 $ 2,700.00
29 Fishing Pier 1 LS $ 79,000.00 $ 79,000.00
30 Picnic Tables 8 EA $ 2,200.00 $ 17,600.00
31 Benches (6') 9 EA $ 1,200.00 $ 10,800.00
32 ISplash Park and Playground Concrete 6,170 SF $ 5.00 $ 30,850.00
Stormwater and Utilities
33 Stormwater Construction 1 LS $ 55,000.00 $ 55,000.00
34 Parking Lighting 1 LS $ 80,000.00 $ 80,000.00
35 Electrical Distribution 1 LS $ 100,000.00 $ 100,000.00
Landscaping
36 Landscaping 1 LS $ 25,000.00 $ 25,000.00
37 llrrigation 1 LS $ 5,000.00 $ 5,000.00
38 lTrash Receptacles 20 EA $ 450.00 $ 9,000.00
Design
39 lEngineering and Permitting 1 LS $ 200,000.00 $ 2001000.00
SUBTOTAL $ 2,691,810.00
Contingency(5%) $ 134,590.50
TOTAL $ 2,826,400.50
Page 2
2131t1M3J43 JO)1110 Karo sa ca o va ns woasaawp m S1SIlN310S•S2133N19N3
sos9-roo£(sa£Pauogd xaj z£1ae Bff.LVtiiaOel'3 -
9o99-b0£199£) lj'a31VM3�Jo3
vo-sso-slatla S1N3W3A021dW1 szlzE a as e,pi,od
'aa 3a1sa3nia
JI21tJd dOlS 3l1SIHM Z0E'uo moa HiaoNrosl
£ivnid3ONOO Na p.\ie s„ow awla's£nsro si enNs oo a�,ew g s�sPa,❑
awvN iO3road
i
r
t
J'
o
rt^r h
r
a a�
IS
v�
LL
r
O � �
G,
O
"a4
I
`r
ww
■
a
O
■
■
■
■ ■
SLOE/£vUL LIVORe,:pet AG Ag D—Z eN 6ulmerp
CITY OF EDGEWATER - WHISTLE STOP PARK
Conceptual Plan Cost Estimate - Option 3
ITEM # DESCRIPTION QTY UNIT PRICE/UNIT PRICE
1 Mobilization/Demobilization 1 LS $ 60,000.00 $ 60,000.00
2 Construction Survey&As-Built Survey 1 LS $ 15,000.00 $ 15,000.00
3 Environmental Compliance 1 LS $ 15,000.00 $ 15,000.00
Earthwork
4 Clearing, Grubbing and Hauling 1 LS $ 20,000.00 $ 20,000.00
5 Demolition and Hauling 1 LS $ 35,000.00 $ 35,000.00
6 Grading and Compaction 1 LS $ 30,000.00 $ 30,000.00
7 Fill 1,000 CY $ 12.00 $ 12,000.00
Hardscape
8 12'Concrete Trail 3,320 LF $ 55.00 $ 182,600.00
9 5'Sidewalk 1,231 LF $ 20.00 $ 24,620.00
10 Type"D"Curb 6,300 LF $ 20.00 $ 126,000.00
11 Asphalt Parking & Roadway 148,000 SF $ 3.00 $ 444,000.00
12 Signage 1 LS $ 10,000.00 $ 10,000.00
13 Striping 1 LS 1 $ 20,000.00 1 $ 20,000.00
14 Entrance Signs 1 2 1 EA 1 $ 5,000.00 1 $ 10,000.00
Buildings
15 N. Restroom Building (inc. electrical and plumbing) 1 LS $ 270,000.00 $ 270,000.00
16 S. Restroom Building (inc.electrical and plumbing) 1 LS $ 97,200.00 $ 97,200.00
17 Renovation Existing Restroom/Storage Building 1 LS $ 115,000.00 $ 115,000.00
18 Building Electrical Connection 2 LS $ 5,000.00 $ 10,000.00
19 Building Water Connection 2 LS $ 15,000.00 $ 30,000.00
20 Building Sewer Connection 2 LS $ 15,000.00 $ 30,000.00
Amenities
21 Splashpark 1,500 SF $ 130.00 $ 195,000.00
22 Playground-Equipment&Soft Surfacing 1 LS $ 150,000.00 $ 150,000.00
23 Skate Park 11,000 SF $ 20.00 $ 220,000.00
24 Dog Park 1 LS $ 25,000.00 $ 25,000.00
25 Basketball Court 1 LS $ 36,000.00 $ 36,000.00
26 Medium Pavilion 4 EA $ 25,000.00 $ 100,000.00
27 Small Pavilions 4 EA $ 10,000.00 $ 40,000.00
28 Grills 12 EA $ 300.00 $ 3,600.00
29 Fishing Pier 1 LS $ 47,000.00 $ 47,000.00
30 Picnic Tables 20 EA $ 2,200.00 $ 44,000.00
31 Benches (6') 9 EA 1 $ 1,200.00 1 $ 10,800.00
32 Splash Park and Playground Concrete 5,850 SF 1 $ 5.00 1 $ 29,250.00
Stormwater and Utilities
33 Stormwater Construction 1 LS $ 79,000.00 $ 79,000.00
34 Splash Park and Playground Lighting 1 LS $ 63,000.00 $ 63,000.00
35 Trail Lighting 1 LS $ 100,000.00 $ 100,000.00
36 Parking Lighting 1 LS $ 150,000.00 $ 150,000.00
37 Electrical Distribution 1 LS $ 100,000.00 $ 100,000.00
Landscaping&Amenities
38 Landscaping 1 LS $ 50,000.00 $ 50,000.00
39 Irrigation 1 LS $ 10,000.00 $ 10,000.00
40 Selective Wetland Clearing and Thinning 1 LS $ 5,000.00 $ 5,000.00
41 Trash Receptacles 20 EA $ 450.00 $ 9,000.00
Design
42 Engineering and Permitting 1 LS $ 200,000.00 $ 200,000.00
SUBTOTAL $ 3,223,070.00
Contingency(5%) $ 161,153.50
TOTAL $ 3,384,223.50
Page 3
2131t1M3J43 JO)1110 N3 sa ca o va ns ---.p--, S1SIlN310S•S2133N19N3
so99-roo£(9a£Pxaj z£1ae BffLVtiia0el3
9099-b0£199£)auogd lj'a31VM3�J03
v0-sso-siatla S1N3W3A021dW1 szizE a as e,pi,od
'aa 3a1sa3nia
JI21tJd dOlS 3l1SIHM 'NO HiaoNro
moa °1
V lt/f11d30N00 N p.\i0 sp,opu awlaZ0E1's£b9ro si enNs oo a�,ew a s�sPa,❑
3WVN 1O3f0i GI
e.. R
v
� Y
m
t
u r
wom�
0
° o
LL
O � 1
g
s
j 1
et g7,
x.
u It�ua
�S
Yom/ 0
•
GO
J ,
1 •
0
• •
m
qp1 Y v §
k R^ F
aatiu(
SLOT/EVNL G� 4e1 DAG Ag W6-00\s-1—dd IS aOsxlM--WP Poa-SfU\SLJ31'W,d D—ZaweNfiuimerp
CITY OF EDGEWATER - WHISTLE STOP PARK
Conceptual Plan Cost Estimate - Option 4
ITEM # DESCRIPTION QTY UNIT PRICE/UNIT PRICE
1 Mobilization/Demobilization 1 LS $ 60,000.00 $ 60,000.00
2 Construction Survey&As-Built Survey 1 LS $ 15,000.00 $ 15,000.00
3 Environmental Compliance 1 LS $ 15,000.00 $ 15,000.00
Earthwork
4 Clearing, Grubbing and Hauling 1 LS $ 20,000.00 $ 20,000.00
5 Demolition and Hauling 1 LS $ 35,000.00 $ 35,000.00
6 Grading and Compaction 1 LS $ 30,000.00 $ 30,000.00
7 Fill 1,000 CY $ 12.00 $ 12,000.00
Hardscape
8 10'Concrete Trail 2,500 LF $ 45.00 $ 112,500.00
9 5'Sidewalk 1,350 LF $ 20.00 $ 27,000.00
10 Type"D"Curb 4,800 LF $ 20.00 $ 96,000.00
11 Asphalt Parking & Roadway 66,000 SF $ 3.00 $ 198,000.00
12 Signage 1 LS $ 10,000.00 $ 10,000.00
13 IStriping 1 1 LS $ 10,000.00 $ 10,000.00
14 lEntrance Signs 1 2 1 EA $ 5,000.00 $ 10,000.00
Buildings
15 Restroom Building (inc.electrical and plumbing) 1 LS $ 270,000.00 $ 270,000.00
16 Renovation Existing Restroom/Storage Building 1 LS $ 115,000.00 $ 115,000.00
17 Building Electrical Connection 2 LS $ 5,000.00 $ 10,000.00
18 Building Water Connection 2 LS $ 15,000.00 $ 30,000.00
19 Building Sewer Connection 2 LS $ 15,000.00 $ 30,000.00
Amenities
20 ISplashpark 1,960 SF $ 130.00 $ 254,800.00
21 Playground-Equipment&Soft Surfacing 1 LS $ 150,000.00 $ 150,000.00
22 Skate Park 11,000 SF $ 20.00 $ 220,000.00
23 Basketball Court 1 LS $ 36,000.00 $ 36,000.00
24 Large Pavilion 2 EA $ 50,000.00 $ 100,000.00
25 Small Pavilions 5 EA $ 10,000.00 $ 50,000.00
26 Grills 7 EA $ 300.00 $ 2,100.00
27 Fishing Pier 360 SF $ 45.00 $ 16,200.00
28 Picnic Tables 15 EA $ 2,200.00 $ 33,000.00
29 Benches (6') 9 EA $ 1,200.00 $ 10,800.00
30 Splash Park and Playground Concrete 4,800 SF $ 5.00 $ 24,000.00
Stormwater and Utilities
31 Stormwater Construction 1 LS $ 55,000.00 $ 55,000.00
32 Parking Lighting 1 LS $ 70,000.00 $ 70,000.00
33 Electrical Distribution 1 LS $ 90,000.00 $ 90,000.00
Landscaping
34 Landscaping 1 LS $ 25,000.00 $ 25,000.00
35 Irrigation 1 LS $ 5,000.00 $ 5,000.00
36 Trash Receptacles 20 EA $ 450.00 $ 9,000.00
Design
37 lEngineering and Permitting 1 LS $ 200,000.00 $ 200,000.00
SUBTOTAL $ 2,456,400.00
Contingency(5%) $ 122,820.00
TOTAL $ 2,579,220.00